The Kuhbrücke/Hildesheim bridge is an unreinforced concrete arch bridge near the city of Hildesheim, dating from 1910. When recalculation showed that the bearing capacity was no longer sufficient, the bridge had to be strengthened.
102
thema
Kuhbrücke/
Hildesheim bridge
1
Strengthening of 100 year old unreinforced concrete arch bridge
The Kuhbrücke/Hildesheim bridge is an unreinforced concrete
arch bridge near the city of Hildesheim, dating from 1910. When
recalculation showed that the bearing capacity was no longer
sufficient, the bridge had to be strengthened. The City of Hildesheim investigated several alternatives, e.g.
building a new bridge at the same place, building a new bridge
at an alternative place and strengthening of the existing bridge.
Because of limited financial capacities, strengthening was the
preferred solution. Structural engineering firm 'matrics engi-
neering' was chosen to search for a technical solution that
- upgrades the bridge for load model 'Brückenklasse 30'
according DIN1072 (1985);
- minimizes effort and costs for the structural measures;
- allows use of old bridge during harvest before strengthening
is done.
The bridge was strengthened in 2016 to upgrade the capacity
for carrying vehicles with maximum weight from 3 ton to 40
ton. The historic arch (fig. 3) and the foundations are further
used. New webs were added by horizontal prestressing to the
arch (fig. 4). A bar post-tensioning system (50 mm) was used
The Kuhbrücke/Hildesheim bridge has an important function,
because it is the single access to an agricultural area owned by
the City of Hildesheim. Recalculation has shown that the
bearing capacity of the bridge is not sufficient to carry ordinary
agricultural machines and traffic loads had been limited to
3 tons maximum for vehicles. Furthermore the bridge and its
equipment showed a lot of damage related to ageing.
thema
Kuhbr?cke Hildesheim bridge 3 2017
103
with innovative and very durable Ultra High Performance
Concrete (UHPC) anchor plates (Hybridanker). Finally a rein-
forced concrete deck slab was added to create a kind of box
section. To reduce thermal stresses in integral bridges it is
planned to develop a bridge deck cooling system in a future
research project, using the Kuhbrücke/Hildesheim as trial
project. To verify the efficiency of the cooling, many tempera-
ture sensors were placed. The operation was finished in June
2016.
Kuhbrücke ? 100 year old structure
The bridge was built as unreinforced concrete arch. The arch is
continuous and supported by two massive abutments with a
span of nearly 25 m. With a thickness of just 500 mm the
bridge is very slender (1:50 ratio of midspan height to span
length) and the arch very flat (1:10 ratio of rise of the arch to
span). Although more than 100 years in service the bridge
showed only minor deficiencies, e.g. a transversal crack of
about 50 mm depth at the bottom side of the arch in its centre
along total width. This might have come from overloading by
traffic, temperature, shrinkage and horizontal movement of
abutments. Concrete testing was done to determine the
concrete strength. Class C16/20 according to Eurocode 2
(2011) was finally found. Based on that strength calculations Hermann Weiher, Katrin Runtemund
matrics engineering GmbH
Andreas Praus
City of Hildesheim
1 Strengthened bridge, finalized
in June 2016
2 Kuhbrücke (1910) before
strengthening
3 Sections of the original structure
4 Side view and sections of the
strengthened structure
2
3
4 prestressing bars
remaining members of old bridge (concrete arch and sandy filler)
new slab
new slab
new web
new web pt bars
pt bars
old arch
new web
old arch
Kuhbr?cke Hildesheim bridge 3 2017
Kuhbrücke Hildesheim bridge 3 2017 104
thema
loads and to improve durability. The strengthened bridge still
needs the high compression resistance of the arch and actively
uses it by transferring the forces through the webs into the arch
which acts like a bottom slab. Of course dead weight of the
bridge is fully transferred by the old arch. The old arch and
new members webs and slab act fully together, similar to a box
girder/arch.
The bridge is far away from public road network and subsequently
de-icing salts are not used. To keep costs small, no sealing was
applied. To improve durability, the calculated crack width in the
slab was limited to 0.2 mm instead of 0.3 mm.
The arch bridge has no hinges and hence very high stresses can
occur due to temperature loading. To avoid massive reinforcing
because of the high stiffness of the new box arch girder the
concept was to allow cracking and limit the crack width to
0.2 mm in the webs. Further limitation of stresses due to restraint
deformation is planned to achieve by actively cooling and
heating the bridge deck (see chapter 'Tempering of bridge deck'.)
Construction
Construction works began in February 2016 with installation
of scaffolding (photo 5a and 5b). The old bridge deck was
completely rebuilt. Only the arch and the filling material
was done and traffic loading finally was limited to vehicle loads
of maximum 3 tons. For the upcoming harvest in autumn 2015,
when thousands of tons of sugar beet root were expected, an
urgent solution was needed. If using this bridge with its limited
capacity, only a solution with conveyor belt and small equally
distributed loads was allowed. Finally the City of Hildesheim
created a temporary access by concrete cylinders thrown into
the river and filled up with earth.
Strengthening concept
The main structural deficiency of the arch bridge is the limited
bending resistance of the arch both in longitudinal and trans-
versal direction. It must be assumed that the sandy filler above
the concrete arch does not act as resistance although it seems
that it has some strength.
New cast in-situ webs with height from lower bound of the
arch to the traffic lane level are added on both sides of the arch.
For monolithically connection to the existing arch, the webs
were cast against roughened surface and stressed together by 50
mm prestressing bars (some 1.5 MN for each bar stressing
force). Time depending losses were very small because of the
age of the existing arch. This prestressing force also solved the
deficiencies in transversal direction. Finally a reinforced
concrete deck slab was added to further help distributing the
5a 5b
105
5 Erection of scaffolding
6 Drilling of tendon holes and detailing of webs (from left)
remained and could be used as formwork for the new members.
The arch was bored horizontally in transversal direction at the
length of 4 m to house the prestressing steel bars (photo 6a and
6b). Vertical and horizontal deflection of borings were very
small. After reinforcing the webs and closing the formwork
webs were poured with C30/37.
Deck slab was poured in second stage and monolithically
connected to the new webs. For transversal prestressing of the
arch a bar system of BBV Systems GmbH was applied according
to ETA-16/0286 (2016) using Macalloy prestressing bars and
'Hybridanker'-anchorages.
It was the first time that Hybridanker-plates were applied for
these prestressing bars. Hybridankers are anchorages made of
ultra-high performance concrete (UHPC). Using these anchor -
ages was beneficial from durability point of view (no steel parts
exposed outside stainless steel cap, photo 8a and 8b) and also
because of very small edge distances. This was proved by
special tests which showed that, due to its stiffness (large thick-
ness), when applied on concrete no extra confinement is
needed (e.g. spiral).
6b 6a
Kuhbr?cke Hildesheim bridge 3 2017
Kuhbrücke Hildesheim bridge 3 2017 106
thema
was in 2011. See Weiher et al. (2012) for more details about
general principles.
The construction was finished in June 2016 with a fully
strengthened arch bridge (photo 1). The position of the arch is
still visible by following the anchorages.
The Hybridanker-plates for this project consisted of a force
transfer unit made of ductile cast iron, confinement with rebar
spiral and precast with Ultra High Strength Concrete with a
compressive strength around 200 MPa. Further features were:
grouting inlet, threads to connect the cap, trumpet made of
polyethylene. The technology is still new; its first application
7
8
107
7 Reinforcement of deck slab and installation of prestressing bars
8 Hybridanker-plate for anchoring 50 mm prestressing bar
9 Temperature sensors (a) and plastic hoses (b)
? PROJECT DETAILS
client City of Hildesheim
contractor Hoch- und Industriebau Celle GmbH,
Hambühren
PT-system BBV Systems GmbH, Bobenheim-Roxheim
design matrics engineering GmbH, München
tempering matrics engineering GmbH, München;
tripleS GmbH, Mülheim an der Ruhr
? REFERENCES
1 DIN 1072. (1985) Straßen- und Wegbrücken. Lastannah-
men. Berlin,Germany: Beuth Verlag GmbH.
2 DIN EN 1992-1-1 Eurocode 2. (Jan 2011) Bemessung und
Konstruktion von Stahlbeton- und Spannbetontragwerken
? Teil 1-1: Allgemeine Bemessungsregeln und Regeln für
den Hochbau.
3 ETA-16/0286. (2016) BBV 1030 post-tensioning bar tendon
system, nominal diameter 32 to 50 mm. Bobenheim-Rox -
heim, Germany: BBV Systems GmbH.
4 Weiher, H., Tritschler, C., Glassl, M., & Hock, S. (2012): Hybri-
danker aus UHPC - Erstanwendung bei der Verstärkung
der Rheinschleuse Iffezheim mit Dauerlitzenankern. Beton-
und Stahlbetonbau Vol. 107, Nr. 4, Ernst & Sohn.
Tempering of bridge deck
The City of Hildesheim was very open-minded for a planned
research project. The restraint stresses due to temperature shall
be limited by tempering the bridge deck. For that purpose
plastic hoses were installed (photo 9a and 9b). The idea is to
send tempered liquid in order to cool down in hot periods
(e.g. summer) or heat up the concrete deck in cold periods (e.g.
winter). By doing so, one may decrease stresses due to tempera-
ture significantly. The project shall be used as trial project and
permanent use is not foreseen. Therefore, the design was done
without considering the benefits of such a tempering. Even
higher effects of tempering can be achieved by this method for
large continuous girder bridges and integral bridges.
Conclusion
A very old concrete bridge built in 1910 was strengthened at
little costs (< 30% of building a new bridge) to meet modern
goals. For this purpose it was beneficial that the bridge was
unreinforced and furthermore had a static system (arch) that
offered hidden resistance.
The strengthening concept was chosen in such a way that the
load on the bridge during construction was not large. Innova-
tive aspects were applied, such as the high strength concrete
anchorages of prestressing bars and the bridge tempering trial
to limit stresses from temperature load.
?
9a 9b
Kuhbr?cke Hildesheim bridge 3 2017
Reacties